Demo mode · Atlas Data Centre Modernisation is a fictional, illustrative programme. Figures are examples. Read-only.Create account
Reports

Executive status report

Current project records

Fictional demo reports are saved for this page session only. AI analysis is available in your signed-in workspace.

ProjectScope 360 · Status report · Illustrative example

Atlas Data Centre Modernisation

As of 16 Nov 2026 · Sponsor: Helen Marlowe, Chief Operating Officer · Owner: Daniel Okafor, Programme Director · Stage: Delivery

Red
  • Budget forecast 6.1% over baseline (>5%)
  • 1 milestone at risk
  • 1 critical open RAID item (score ≥ 20)

Migrate 420 workloads from two ageing on-premises data centres to a modern hybrid estate (colocation plus public cloud) and exit the Croydon facility.

Five-scope overview

ScopeRAGReadinessChecklistReasoning
Purpose & GovernanceGreen91%7/8Readiness at or above 70% with no overdue items
Scope & PlanningAmber100%7/71 overdue item; Budget forecast 6.1% over baseline
People & ResourcesGreen80%5/7Readiness at or above 70% with no overdue items
Delivery & AssuranceRed83%6/82 overdue items; 1 open RAID item scoring 20+
Outcomes & LearningAmber50%2/7Readiness 50% (below 70%); 1 benefit off track

Budget

Baseline
£8,400,000
Forecast
£8,910,000
Actual to date
£4,870,000
Variance
£510,000 (6.1%)

Overdue items (3)

  • Croydon decommissioning plan — Deliverables (WBS), due 6 Nov 2026
  • Inter-site latency above 8 ms during peak — RAID register, due 10 Nov 2026
  • AI-generated runbooks reviewed — Quality & sign-off, due 13 Nov 2026

Milestones

MilestoneDueOwnerStatus
Business case approved18 Feb 2026Helen MarloweComplete
Colocation ready for service30 Jun 2026Marcus LeeComplete
Wave 2 complete4 Sep 2026Priya ShahComplete
Wave 3 cut-over11 Dec 2026Priya ShahAt risk
Service desk trained on new estate29 Jan 2027Aisha BelloOn track
Wave 4 complete12 Mar 2027Priya ShahPlanned
Croydon exit30 Jun 2027Sam TurnerPlanned

Top open RAID items

TypeItemScoreOwnerAction
RiskFirewall rule-base complexity delays wave 320Marcus LeeRationalise rules in two sprints; add second security engineer.
IssueInter-site latency above 8 ms during peak16Marcus LeeUpgrade cross-connect to 2×10G.
RiskLegacy app licence not portable to cloud9Priya ShahVendor negotiation; fallback to colocation.
DependencyIdentity platform upgrade (separate project)9Daniel OkaforJoint plan with IAM programme.
AssumptionCroydon lease cannot be extended beyond June 20278Sam Turner—

Proof of Value · benefits versus target

With baseline, target & actual
4/4
At or beyond target
0
Missing measurement data
0

Targets are compared with recorded actuals from their baseline, including reduction targets. Missing values are not evidence of realised value.

BenefitBaselineTargetActualProgressOwnerStatus
Annual run-cost reduction0 £k1600 £k520 £k33%Finance Business PartnerOn track
Power usage reduction0 %40 %18 %45%Sustainability LeadTracking
Service availability99.5 %99.95 %99.9 %89%Head of OperationsOn track
Mean time to recover6 hrs2 hrs5 hrs25%Head of OperationsOff track

Decisions

  • Approve full business case — Investment Committee, 18 Feb 2026Approved
  • Select colocation partner (Northgate Colo) — Programme Board, 9 Apr 2026Approved
  • Wave 2 go-live (CAB-0412) — Change Advisory Board, 21 Aug 2026Approved
  • Defer mainframe migration to phase 2 — Helen Marlowe, 15 Sep 2026Approved
  • Wave 3 cut-over window (CAB-0457) — Change Advisory Board, 20 Nov 2026Proposed

Suggested actions (rule-based)

  1. Review cost forecast with the sponsor: forecast is 6.1% above baseline.
  2. Escalate "Firewall rule-base complexity delays wave 3" (score 20) — owner Marcus Lee.
  3. Escalate "Inter-site latency above 8 ms during peak" (score 16) — owner Marcus Lee.
  4. Clear 3 overdue items; oldest: "Croydon decommissioning plan".
  5. Take 2 pending change requests to the next change board.

Rules: budget variance >5% amber, >10% red; RAID score (severity × probability) ≥12 high, ≥20 critical; scope readiness <70% amber, <35% red; any overdue item flagged; readiness = 70% checklist + 30% register evidence.