Executive status report
Current project records
Fictional demo reports are saved for this page session only. AI analysis is available in your signed-in workspace.
Atlas Data Centre Modernisation
As of 16 Nov 2026 · Sponsor: Helen Marlowe, Chief Operating Officer · Owner: Daniel Okafor, Programme Director · Stage: Delivery
- Budget forecast 6.1% over baseline (>5%)
- 1 milestone at risk
- 1 critical open RAID item (score ≥ 20)
Migrate 420 workloads from two ageing on-premises data centres to a modern hybrid estate (colocation plus public cloud) and exit the Croydon facility.
Five-scope overview
| Scope | RAG | Readiness | Checklist | Reasoning |
|---|---|---|---|---|
| Purpose & Governance | Green | 91% | 7/8 | Readiness at or above 70% with no overdue items |
| Scope & Planning | Amber | 100% | 7/7 | 1 overdue item; Budget forecast 6.1% over baseline |
| People & Resources | Green | 80% | 5/7 | Readiness at or above 70% with no overdue items |
| Delivery & Assurance | Red | 83% | 6/8 | 2 overdue items; 1 open RAID item scoring 20+ |
| Outcomes & Learning | Amber | 50% | 2/7 | Readiness 50% (below 70%); 1 benefit off track |
Budget
- Baseline
- £8,400,000
- Forecast
- £8,910,000
- Actual to date
- £4,870,000
- Variance
- £510,000 (6.1%)
Overdue items (3)
- Croydon decommissioning plan — Deliverables (WBS), due 6 Nov 2026
- Inter-site latency above 8 ms during peak — RAID register, due 10 Nov 2026
- AI-generated runbooks reviewed — Quality & sign-off, due 13 Nov 2026
Milestones
| Milestone | Due | Owner | Status |
|---|---|---|---|
| Business case approved | 18 Feb 2026 | Helen Marlowe | Complete |
| Colocation ready for service | 30 Jun 2026 | Marcus Lee | Complete |
| Wave 2 complete | 4 Sep 2026 | Priya Shah | Complete |
| Wave 3 cut-over | 11 Dec 2026 | Priya Shah | At risk |
| Service desk trained on new estate | 29 Jan 2027 | Aisha Bello | On track |
| Wave 4 complete | 12 Mar 2027 | Priya Shah | Planned |
| Croydon exit | 30 Jun 2027 | Sam Turner | Planned |
Top open RAID items
| Type | Item | Score | Owner | Action |
|---|---|---|---|---|
| Risk | Firewall rule-base complexity delays wave 3 | 20 | Marcus Lee | Rationalise rules in two sprints; add second security engineer. |
| Issue | Inter-site latency above 8 ms during peak | 16 | Marcus Lee | Upgrade cross-connect to 2×10G. |
| Risk | Legacy app licence not portable to cloud | 9 | Priya Shah | Vendor negotiation; fallback to colocation. |
| Dependency | Identity platform upgrade (separate project) | 9 | Daniel Okafor | Joint plan with IAM programme. |
| Assumption | Croydon lease cannot be extended beyond June 2027 | 8 | Sam Turner | — |
Proof of Value · benefits versus target
- With baseline, target & actual
- 4/4
- At or beyond target
- 0
- Missing measurement data
- 0
Targets are compared with recorded actuals from their baseline, including reduction targets. Missing values are not evidence of realised value.
| Benefit | Baseline | Target | Actual | Progress | Owner | Status |
|---|---|---|---|---|---|---|
| Annual run-cost reduction | 0 £k | 1600 £k | 520 £k | 33% | Finance Business Partner | On track |
| Power usage reduction | 0 % | 40 % | 18 % | 45% | Sustainability Lead | Tracking |
| Service availability | 99.5 % | 99.95 % | 99.9 % | 89% | Head of Operations | On track |
| Mean time to recover | 6 hrs | 2 hrs | 5 hrs | 25% | Head of Operations | Off track |
Decisions
- Approve full business case — Investment Committee, 18 Feb 2026Approved
- Select colocation partner (Northgate Colo) — Programme Board, 9 Apr 2026Approved
- Wave 2 go-live (CAB-0412) — Change Advisory Board, 21 Aug 2026Approved
- Defer mainframe migration to phase 2 — Helen Marlowe, 15 Sep 2026Approved
- Wave 3 cut-over window (CAB-0457) — Change Advisory Board, 20 Nov 2026Proposed
Suggested actions (rule-based)
- Review cost forecast with the sponsor: forecast is 6.1% above baseline.
- Escalate "Firewall rule-base complexity delays wave 3" (score 20) — owner Marcus Lee.
- Escalate "Inter-site latency above 8 ms during peak" (score 16) — owner Marcus Lee.
- Clear 3 overdue items; oldest: "Croydon decommissioning plan".
- Take 2 pending change requests to the next change board.
Rules: budget variance >5% amber, >10% red; RAID score (severity × probability) ≥12 high, ≥20 critical; scope readiness <70% amber, <35% red; any overdue item flagged; readiness = 70% checklist + 30% register evidence.