Demo mode · Atlas Data Centre Modernisation is a fictional, illustrative programme. Figures are examples. Read-only.Create account

Project team

Manage team
  • Priya Shah

    Migration lead

  • Marcus Lee

    Network architect

  • Aisha Bello

    Service transition manager

  • Sam Turner

    Decommissioning manager

Executive dashboard · as of 16 Nov 2026

Atlas Data Centre Modernisation

Migrate 420 workloads from two ageing on-premises data centres to a modern hybrid estate (colocation plus public cloud) and exit the Croydon facility.

Project health
Red
Budget forecast 6.1% over baseline (>5%)
Scope completeness
81%
Mean readiness of five scopes
Milestones
3/7
Next: Wave 3 cut-over · 11 Dec 2026
Open RAID
5
2 scoring 12 or more
Budget variance
+6.1%
£8.9m forecast vs £8.4m (example)
Overdue actions
3
Across all registers
Benefits progress
48%
4 benefits · mean progress to target

Live alerts (3)

Fictional example · As of 2026-11-16

Forward outlook · 16 Nov 2026

Recorded completion forecast
£8.9m
£4,040,000 remaining against actuals
Constant-spend scenario
£8.7m
Actual spend ÷ elapsed project time. Assumes even spend; not an approved forecast.
Next 30 days
1
1 milestones marked at risk or blocked
Upcoming milestones
  • Wave 3 cut-over

    11 Dec 2026 · Priya Shah · At risk · Dependency: CAB-0457 approval

Priority risk exposure
  • Firewall rule-base complexity delays wave 3 · 20/25

    Marcus Lee · Rationalise rules in two sprints; add second security engineer.

  • Legacy app licence not portable to cloud · 9/25

    Priya Shah · Vendor negotiation; fallback to colocation.

Project milestones

View calendar

Risk checks

Risk register

AI project insights

AI insights configuration

AI analysis requires a signed-in workspace with stored records.

Saved report analysis

Five scopes

Readiness by scope

Insights from rules

  • Review cost forecast with the sponsor: forecast is 6.1% above baseline.
  • Escalate "Firewall rule-base complexity delays wave 3" (score 20) — owner Marcus Lee.
  • Escalate "Inter-site latency above 8 ms during peak" (score 16) — owner Marcus Lee.
  • Clear 3 overdue items; oldest: "Croydon decommissioning plan".

Generated from stored records using fixed thresholds — see the report for the full logic.

Recent decisions

Decision log
  • Wave 3 cut-over window (CAB-0457)
    Change Advisory Board · 20 Nov 2026
    Proposed
  • Defer mainframe migration to phase 2
    Helen Marlowe · 15 Sep 2026
    Approved
  • Wave 2 go-live (CAB-0412)
    Change Advisory Board · 21 Aug 2026
    Approved
  • Select colocation partner (Northgate Colo)
    Programme Board · 9 Apr 2026
    Approved

Activity

  • Updated RAID item · Firewall rule-base complexity delays wave 3
    14 Nov 2026, 16:20
  • Added decision · Wave 3 cut-over window (CAB-0457)
    13 Nov 2026, 10:05
  • Updated benefit · Annual run-cost reduction
    11 Nov 2026, 09:40
  • Added change request · Bring forward wave 4 by two weeks
    9 Nov 2026, 14:12
  • Updated milestone · Wave 3 cut-over
    6 Nov 2026, 11:30