Atlas Data Centre Modernisation
Live alerts (3)
Fictional example · As of 2026-11-16
- Budget forecast above threshold
£510,000 (6.1%) over baseline · threshold 5%
- Firewall rule-base complexity delays wave 3
Risk · score 20 · owner Marcus Lee
- Inter-site latency above 8 ms during peak
Issue · score 16 · 6 days overdue · owner Marcus Lee
People & Resources
People
Stakeholders, accountability and capacity — shared with the People & Resources scope.
Influence / interest grid
Interest: Low
Interest: Medium
Interest: High
Influence: High
Information Security
Helen Marlowe
Influence: Medium
Service Owners Forum
Influence: Low
Facilities (Croydon)
Capacity vs allocation (%)
Stakeholder register (4)
Influence, interest and the communication each stakeholder needs.
| Helen Marlowe | Sponsor / COO | High | High | Fortnightly | Supportive |
| Service Owners Forum | Business service owners | Medium | High | Per wave | Concerned |
| Information Security | CISO office | High | Medium | Monthly | Neutral |
| Facilities (Croydon) | Site management | Low | High | Monthly | Neutral |
RACI assignments (6)
Who is Responsible, Accountable, Consulted and Informed.
| Wave cut-over approval | Change Advisory Board | A |
| Wave cut-over execution | Priya Shah | R |
| Wave cut-over execution | Information Security | C |
| Benefits tracking | Finance Business Partner | R |
| Benefits tracking | Helen Marlowe | A |
| Service desk readiness | Aisha Bello | R |
Resource allocation (4)
Capacity against allocation to spot over-commitment.
| Priya Shah | Migration lead | 100 | 110 | 31 Mar 2027 |
| Marcus Lee | Network architect | 80 | 75 | 31 Jan 2027 |
| Aisha Bello | Service transition manager | 60 | 50 | 30 Jun 2027 |
| Sam Turner | Decommissioning manager | 50 | 40 | 30 Jun 2027 |
Suppliers (3)
Supplier interfaces, contract values and renewal dates.
| Northgate Colo | Colocation and cross-connects | £2,100,000 | 30 Jun 2031 | Active |
| Meridian Migration Services | Migration factory | £1,450,000 | 30 Apr 2027 | Active |
| Clearview Security | Penetration testing | £85,000 | 28 Feb 2027 | Under review |